Hi everyone – The DSRIP timeline has been updated and appears below. You can access a prettier version at https://www.health.ny.gov/health_care/medicaid/redesign/dsrip/docs/dsrip_timeline.pdf
Any questions may be directed to [email protected]
December 1 | Leads to submit final partner lists in Network Tool |
December 1 | Optional: Project Plans Applications completed by PPSs for DSRIP Support Team review |
December 2 | Project Plan Application Tool published (Sections 1-9, except Section 4) |
December 3 | Scale and Speed of Application template released by DSRIP Support Team to PPS Leads |
Early December | VAP Exception Results published |
December 10 | Project Plan Application Tool (Sections 4, 10, 11) published |
(no later than) December 16 |
Scale and Speed of Application responses due from PPS Leads to KPMG |
December 22 | Project Plan Application completed and submitted by PPS Lead |
December 24 | Independent Assessor completes DSRIP Project Plan checklist review of each application |
December 24 | DSRIP Project Plan Application PDFs posted to web, public comment period on Project Plan Applications begins |
January 26 | Public comment period on Project Plan Applications ends |
Mid-January | Finalized Attribution for Valuation Results Released |
February 2 | Independent Assessor recommendations made public |
Mid-February | DSRIP Project Approval & Oversight Team public hearings & meetings re: IA recommendations, makes final recommendations to state |
Mid-Late February | Final attribution results released |
February 20 | Capital Restructuring Financing application due |
March 1 | Implementation Plan due from PPSs |
Early March | DSRIP Project Plan awards made |
April 1 | DSRIP Year 1 begins |
Mid-April | First Year 1 Payment to PPSs |